Question: Please help me construct an activity on node network diagram for the above Gantt chart using the ES, EF, LS, LF, Act. name and duration

Please help me construct an activity on node network diagram for the above Gantt chart using the ES, EF, LS, LF, Act. name and duration notation.

Find the critical path and calculate time to completion. Please annotate these two items and please draw out how the diagram and critical path are supposed to look in graphic format, I am very confused on how it is supposed to look.

ACTIVITY A: Aircraft stops at PLAN PLAN START DURATION gate 0 0 

ACTIVITY A: Aircraft stops at PLAN PLAN START DURATION gate 0 0 B: Jet bridge connected 0 5 C: Passengers deplane 5 10 D: Baggage Offloaded 15 15 E: Refueling/water servicing 25 25 F: Galley servicing 40 20 G: Cabin cleaning 40 20 H: Baggage loaded 55 15 I: Passengers boarded 55 15 J: Aircraft ready for departure 70 85

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!