Question: Please help me draw a schedule and network diagram as I'm struggling with it. Please help and guide me on this. Thank you. The following
Please help me draw a schedule and network diagram as I'm struggling with it. Please help and guide me on this.
Thank you.
The following table is an activity list that includes the duration and predecessor for a series of project activities. Draw a schedule network diagram and calculate the duration of the critical path.
| Activity | Duration | Predecessor |
|---|---|---|
| A | 2 | Start |
| B | 4 | A, E |
| C | 6 | A |
| D | 3 | B, C |
| E | 7 | Start |
| F | 2 | E |
| End | - | D, F |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
