Question: Please help me draw a schedule and network diagram as I'm struggling with it. Please help and guide me on this. Thank you. The following

Please help me draw a schedule and network diagram as I'm struggling with it. Please help and guide me on this.

Thank you.

The following table is an activity list that includes the duration and predecessor for a series of project activities. Draw a schedule network diagram and calculate the duration of the critical path.

Activity Duration Predecessor
A 2 Start
B 4 A, E
C 6 A
D 3 B, C
E 7 Start
F 2 E
End - D, F