Question: Please help me find the Early Finish (EF) An activity in a network has the following characteristics: LS=23, duration =6, and slack is 5 .
Please help me find the Early Finish (EF)
An activity in a network has the following characteristics: LS=23, duration =6, and slack is 5 . EF = 18 24 29 35