Question: Please help me i will give good rating 2 3 X b) Company Zen was awarded a project to complete the activities. The following table

Please help me i will give good rating

Please help me i will give good rating 2 3 X b)

2 3 X b) Company Zen was awarded a project to complete the activities. The following table shows the activities, durations and the preceding activities. Activity Preceding Activity Durations (days) A 5 B 2 3 D B 4 E 6 F B, C 7 G E 4 H D, E 5 1 G H 5 J FI 4 K J 3 Draw a network planning for the project. Hence, state the critical paths