Question: please help me in this one Question 13 (1 point) Saved The following two activities (D and E) are candidates for crashing on a CPM

please help me in this one
please help me in this one Question 13 (1 point)
Question 13 (1 point) Saved The following two activities (D and E) are candidates for crashing on a CPM network. To reduce one week from the project duration, which of the following activity should be crashed first? How much will extra cost add to the total project cost by crashing that particular activity? Activity Normal time Crash time Normal cost Crash cost D 5 weeks 3 weeks $900 $1,200 E 8 weeks 5 weeks $1,000 $1,600 D; $150 D; $300 E; $600 E; $200