Question: Please help me solve the question Courtney is a programmer receiving requests each week to analyze a large data base. Five jobs were on her

Please help me solve the question
Courtney is a programmer receiving requests each week to analyze a large data base. Five jobs were on her desk Monday morning, and she must decide in what order to write the code. Assume that all jobs arrived today (day 1 and hour 1), in the order shown below. Courtney has assigned the number of hours required to do the coding as noted. Note that Courtney works an 8-hour day and today is a work day. JOB A B DUE DATE (HOURS HENCE) 10 16 12 24 32 DURATION (HOURS REQUIRED) 6 3 7 8 15 cowo E a) Sequence the jobs according to EDD. According to the EDD rule, the sequence of jobs should beStep by Step Solution