Question: Please Help me sove for C Suad Alwan the purchasing agent for Dubai Airlines, has determined that the third place took 1 8 0 0

Please Help me sove for C
Suad Alwan the purchasing agent for Dubai Airlines, has determined that the third place took 18000 hours to produce. using an 80% learning curve and a $30-per-hour labor charge, he wants to determine the cost of the four additional planes.
A.) Time required for the fourth unit =16,408 hours (round your response to the nearest whole number).
B.) Cost of the fourth unit =492240 dollars (round your response to the nearest whole number).
C.) Time required for the fifth unit = hours (round your response to the nearest whole number).