Question: Please help me understand my homework 1. A project has the following estimated data: price= $95 per unit, variable cost= 42.75 per unit; fixed costs=
Please help me understand my homework
1. A project has the following estimated data: price= $95 per unit, variable cost= 42.75 per unit; fixed costs= $5,700; required = 13 percent; initial investment =$12,000; life =six years. Ignore the effect of taxes.
What is the accounting break-even quantity?
What is the cash break-even quantity?
What is the financial break-even quantity?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts