Question: Please help me with A B C D The following table shows estimates of activity times (weeks) for a project: Act. Opt.Time Probable Time Pessimistic
Please help me with A B C D
The following table shows estimates of activity times (weeks) for a project:
Act. Opt.Time Probable Time Pessimistic Time
A 3 4 5
B 1.5 2 2.5
C 5 6 7
D 4 4.5 8
E 5 6 7
F 1 2 3
G 7 9 11
Suppose that the critical path is A-C-E-F-G. Do not round intermediate calculations. Round your answers to three decimal places
A. What is the probability that the project will be compeleted within 28 weeks
B. What is the probability that the project will be compeleted within 25 weeks
C. What is the probability that the project will be compeleted within 26 weeks
D. What is the probability that the project will be compeleted within 27 weeks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock