The following table shows estimates of activity times (weeks) for a project:
Act. Opt.Time Probable Time Pessimistic Time
A 3 4 5
B 1.5 2 2.5
C 5 6 7
D 4 4.5 8
E 5 6 7
F 1 2 3
G 7 9 11
Suppose that the critical path is A-C-E-F-G. Do not round intermediate calculations. Round your answers to three decimal places
A. What is the probability that the project will be compeleted within 28 weeks
B. What is the probability that the project will be compeleted within 25 weeks
C. What is the probability that the project will be compeleted within 26 weeks
D. What is the probability that the project will be compeleted within 27 weeks
0 19 Homework: Project Management The following table shows estimates of activity times (In weeks) for a project: Optimistic Time Most probable Time Pessimistic Time Activity 7 4 5 2 2.5 C 5 0 45 D E E 5 6 2 2 11 Suppose that the tical path in AC- Use Appendix Atonower the questions Dorot round Intermediate calculation Round your answers to three decimal places What is the probably that the project will completed within 2 we b. What is the probability that the project will be completed within a week What the probability that the project will be completed in than 20 W d. What is the ability that the two complete in 2 we 2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!