Question: Please help me with part d . The following tasks are to be performed on an assembly line: awarded The following tasks are to be

Please help me with part d. The following tasks are to be performed on an assembly line:
awarded
The following tasks are to be performed on an assembly line:
The workday is 6.25 hours long. The demand for completed product is 500 per day.
a. Find the cycle time required to meet the desired output rate.
Note: Round your answer to 1 decimal place.
Cycle time
45.0
seconds per unit
b. What is the theoretical number of workstations required to meet the desired output rate?
Note: Round up your answer to the next whole number.
d. Balance the line using sequential restrictions and the longest-operating-time rule. Determine the task under each workstation and
the idle time for each such task.
Note: Leave no cells blank - be certain to enter "O" wherever required. Round your answers to 1 decimal place.
e. What is the efficiency of the line balanced as in part (d) assuming it is running at the cycle time determined in part (a)?
 Please help me with part d. The following tasks are to

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!