Question: please help me with this. i am new student. will give likes. please. thank you. with solution if possible * The graph paper formula list
please help me with this. i am new student. will give likes. please. thank you. with solution if possible
* The graph paper formula list and normal distribution table a are provided. 1 pts D Question 32 The following activities are listed with normal time, crash time and the corresponding costs for the new project. Determine the cost slope for each activity in the given table. Activity Immedinte Predecessors Normal Crash Time Time (months) (months) Normal Cost (RM) Crash Cost (RM) - (A (B) (C B D E F G H 7 11 5 1 7 1 6 3 AB B D CE D F G Cost Slope (RM month) (A) (B) ( (D) (E) (5) (G) (H) 700.000 800,000 500,000 700.000 900 000 1020,000 300,000 450,000 250,000 430,000 400.000 700,000 500 000 800,000 600 000 750 000 IG (H Table 2 Calculate the direct cost of the project if there is an indirect cost of RM55.000 per month. The direct cost is RM Previous Next > * The graph paper formula list and normal distribution table a are provided. 1 pts D Question 32 The following activities are listed with normal time, crash time and the corresponding costs for the new project. Determine the cost slope for each activity in the given table. Activity Immedinte Predecessors Normal Crash Time Time (months) (months) Normal Cost (RM) Crash Cost (RM) - (A (B) (C B D E F G H 7 11 5 1 7 1 6 3 AB B D CE D F G Cost Slope (RM month) (A) (B) ( (D) (E) (5) (G) (H) 700.000 800,000 500,000 700.000 900 000 1020,000 300,000 450,000 250,000 430,000 400.000 700,000 500 000 800,000 600 000 750 000 IG (H Table 2 Calculate the direct cost of the project if there is an indirect cost of RM55.000 per month. The direct cost is RM Previous Next >