A project consists of the activities in the following table. Times are given in weeks

Activity Preceding Time
A 2
B 3
C A 7
D A, B 3
E C 4
F D 6
  1. Draw the network diagram
  2. Calculate the ES, EF, LS, LF, and slack for each activity
  3. What is this project completion time?