A project consists of the activities in the following table. Times are given in weeks
| Activity | Preceding | Time |
| A | 2 | |
| B | 3 | |
| C | A | 7 |
| D | A, B | 3 |
| E | C | 4 |
| F | D | 6 |
- Draw the network diagram
- Calculate the ES, EF, LS, LF, and slack for each activity
- What is this project completion time?