Question: PLEASE HELP NEED HELP SOON 1. Acme Inc. has the following information available: Actual price paid for material $1.00 Standard price for material $0.90 Actual
1. Acme Inc. has the following information available:
| Actual price paid for material | $1.00 |
| Standard price for material | $0.90 |
| Actual quantity purchased and used in production | 90 |
| Standard quantity for units produced | 100 |
| Actual labor rate per hour | $15 |
| Standard labor rate per hour | $14 |
| Actual hours | 200 |
| Standard hours for units produced | 220 |
A. Compute the material price and quantity, and the labor rate and efficiency variances. Enter all amounts as positive numbers.
| Material price variance | $fill in the blank 1 | FavorableUnfavorable |
| Material quantity variance | $fill in the blank 3 | FavorableUnfavorable |
| Labor rate variance | $fill in the blank 5 | FavorableUnfavorable |
| Labor efficiency variance | $fill in the blank 7 | FavorableUnfavorable |
B. What are some possible causes for this combination of favorable and unfavorable variances?
| Actual price paid for material | $1.00 |
| Standard price for material | $0.80 |
| Actual quantity purchased and used in production | 110 |
| Standard quantity for units produced | 120 |
| Actual labor rate per hour | $14 |
| Standard labor rate per hour | $15 |
| Actual hours | 190 |
| Standard hours for units produced | 210 |
A. Compute the material price and quantity, and the labor rate and efficiency variances. Enter all amounts as positive numbers.
| Material price variance | $fill in the blank 1 | FavorableUnfavorable |
| Material quantity variance | $fill in the blank 3 | FavorableUnfavorable |
| Labor rate variance | $fill in the blank 5 | FavorableUnfavorable |
| Labor efficiency variance | $fill in the blank 7 | FavorableUnfavorable |
B. What are some possible causes for this combination of favorable and unfavorable variances?
| Actual price paid for material | $1.00 |
| Standard price for material | $0.80 |
| Actual quantity purchased and used in production | 110 |
| Standard quantity for units produced | 120 |
| Actual labor rate per hour | $14 |
| Standard labor rate per hour | $15 |
| Actual hours | 190 |
| Standard hours for units produced | 210 |
A. Compute the material price and quantity, and the labor rate and efficiency variances. Enter all amounts as positive numbers.
| Material price variance | $fill in the blank 1 | FavorableUnfavorable |
| Material quantity variance | $fill in the blank 3 | FavorableUnfavorable |
| Labor rate variance | $fill in the blank 5 | FavorableUnfavorable |
| Labor efficiency variance | $fill in the blank 7 | FavorableUnfavorable |
B. What are some possible causes for this combination of favorable and unfavorable variances?
3.
Acme Inc. has the following information available:
| Actual price paid for material | $1.00 |
| Standard price for material | $1.20 |
| Actual quantity purchased and used in production | 110 |
| Standard quantity for units produced | 140 |
| Actual labor rate per hour | $14 |
| Standard labor rate per hour | $16 |
| Actual hours | 200 |
| Standard hours for units produced | 210 |
A. Compute the material price and quantity, and the labor rate and efficiency variances. Enter all amounts as positive numbers.
| Material price variance | $fill in the blank 1 | FavorableUnfavorable |
| Material quantity variance | $fill in the blank 3 | FavorableUnfavorable |
| Labor rate variance | $fill in the blank 5 | FavorableUnfavorable |
| Labor efficiency variance | $fill in the blank 7 | FavorableUnfavorable |
B. What are some possible causes for this combination of favorable and unfavorable variances?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts