Question: PLEASE HELP ON BELOW QUESTION ON SOFTWARE PROJECT MANAGEMENT ------------------------------------------------------------------------------------------------------------------------------------------------- The shortest total length of a project is determined by the longest path through a

PLEASE HELP ON BELOW QUESTION ON SOFTWARE PROJECT MANAGEMENT

PLEASE HELP ON BELOW QUESTION ON SOFTWARE PROJECT

PLEASE HELP ON BELOW QUESTION ON SOFTWARE PROJECT

-------------------------------------------------------------------------------------------------------------------------------------------------

PLEASE HELP ON BELOW QUESTION ON SOFTWARE PROJECT

PLEASE HELP ON BELOW QUESTION ON SOFTWARE PROJECT

"The shortest total length of a project is determined by the longest path through a network diagram." Explain the concept behind this statement [3 marks] The table below shows the breakdown structure for the second sprint of a software development project. Tasks Dependency Duration (days) 8 A A 5 B 6 D 8 BH D, F CI 9 3 E F G H I 7 8 G H 9 J K L 2 J J 3 (i) Create an Activity on Node (AON) network activity diagram for the Project. Your AON should include the following elements: the total duration of the project, its early start time, early finish time, late start time, late finish time, Slack for each activity. [8 marks] Indicate the project's critical path and total duration. Given the following COCOMO constants table: Organic Semi-detached Embedded 2.4 3.0 3.6 b 1.04 1.12 1.2 C 2.5 2.5 2.5 d 0.37 0.35 0.32 Assume that you are to use COCOMO to estimate a project. The project is a rather simple stand-alone utility for a computer running Linux. A person in your team who has done this before estimates the total lines of code to be 36,000. The program must be written in Python. All the rest of the members on your team are experienced. The team is very fluent in Linux and Python. All other factors can be considered to be nominal Using basic COCOMO, estimate the following for this project: the man-months required, [3 marks] the development time, [3 marks] (iii) the number of developers to be allocated for this project. ID The table below shows the breakdown structure for Sprint 3 of the above project. Task Description Immediate Optimistic Most Pessimistic Predecessors Time (in Likely Time (in days) Time (in days) days) 1 Collect 1 2 3 requirements 2 Analyse 1 1 2 9 Processes 3 Analyse Data 2 1 3 5 4 Design Process 2 3 7 11 5 Design Data 2 2 4 18 6 Design Screens 3,4 1 1 7 Design reports 2 3 16 8 Program 6,7 1 4 7 9 Test 7 2 6 22 Document 10 Client Demo 8,9 1 7 4,5 and Create an Activity on Node (AON) network activity diagram for the Project. Your AON should include the following elements: each activity Time Estimate (TE) (rounding to the nearest integer), the total duration of the project its early start time early finish time late start time late finish time Slack for each activity [8 marks] . Indicate the project's critical path and total duration. [1 marks] Based on the Table from part (f) state two resource allocation problems that the project manager may encounter. [2x2 marks]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!