Question: Please help. Please show step by step. I have asked this question already and it was wrong. 3. Pirmin's Bike Shop is behind on a

Please help. Please show step by step. I have asked this question already and it was wrong.

3. Pirmin's Bike Shop is behind on a custom bike and needs to crash 8 hours of time from the 8-step project. (10 points)

Activity

Normal

Duration (hours)

Normal

Cost ($)

Crash

Duration (hours)

Crash

Cost (S)

Immediate

Predecessors

Crash $ per hour

How Many Hours

Slack

A

2

$10

2

$10

None

B

3

$15

2

$23

A

C

5

$25

3

$37

B

D

3

$20

1

$24

B

E

6

$30

4

$44

C

F

1

$5

1

$5

C

G

7

$35

6

$45

E, F

H

10

$50

7

$77

D,G

  1. Draw the network diagram. (2.5 points)
  2. Given the project table above calculate the crash cost for 8 hours of time-savings. (2.5 points)

Suppose Pirmin calls the customer and asks for a project extension, reducing the amount of time he needs to crash.

  1. Calculate the maximum time-savings available on a $20 crash budget and given the crash sequence (2.5 points)
  2. Calculate the cost to crash four hours of savings and give the crash sequence. (2.5 points)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!