Question: Please Help! Proactive project managers can take several actions to control project performance. Which type of project control emphasis does a project manager demonstrate by

Please Help!

Proactive project managers can take several actions to control project performance. Which type of project control emphasis does a project manager demonstrate by identifying where changes have occurred, ensuring the changes are necessary, and managing the implementation of changes?

a.Procurement Control b.Scope Control c.Quality Control d.Cost Control

Assume you have reviewed your most recent project performance report and determined that your project is currently experiencing schedule performance problems. Which of the following strategies represents a potential strategy to improve your schedule performance?

a.Reduce resources to extend the duration of selected activities. b.Overlap activities when possible. c.Examine resource needs and replace rapid, proficient workers with less expensive and less experienced workers. d.Restrict requests for overtime.

Which basis of differentiation is illustrated by a defense contractor that creates major subunits to include: Naval Contracts and Services, Air Force Contracts and Services, and Army Contracts and Services?

a.Functional b.Territorial c.Product d.Customer

Which of the following organizational types provides efficient utilization of resources between projects, but creates a dual reporting relationship for project team members?

a.Functional organization b.Project(ized) organization c.Matrix organization d.Hybrid organization

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!