Question: Please help problem 1 ( no 1 - 6 ) Problem 1 Use the basic building layout shown below and determine the requested loads using

Please help problem 1(no1-6)
Problem 1
Use the basic building layout shown below and determine the requested loads using the ASCE 7 tables provided on the course website. You do not need to consider the self weight of the structural members.
The roof of the building is flat. It is composed of 4-ply felt and gravel on 3-inches of reinforced concrete. The ceiling beneath the roof is a suspended steel channel system. The building is a storage facility located on the UW campus in a fully exposed area.
a. The roof dead load
b. The flat roof snow load in psf to be applied across the roof. Note all assumptions you make related to various factors associated with Equation 7.3-1.
c. The live load in psf to be applied to Column B2
The roof of the building is flat and there is a 3-inch parapet wall surrounding the perimeter. Drainage is managed through pipes located flush with the roof, and secondary drainage occurs by overtopping the 3-inch parapet wall. It is composed of 2-inches of reinforced concrete on 18-gauge metal decking. A single-ply waterproof sheet will be used. The ceiling beneath the roof is unfinished, but allowance for mechanical ducts should be provided.
a. The roof dead load
b. The rain load in psf to be applied across the roof
The dead load and live load for the second floor of a library in which any area can be used for stacks. Assume that there will be a steel channel ceiling system and asphalt tile floors. The floors are 6-inch reinforced concrete. Allowance should be provided for mechanical ducts.
The dead load and live load for a floor in a light manufacturing warehouse/office complex in which any area can be used for storage. Assume that there will be no ceiling or floor finish and that the floors are 4-inch reinforced concrete. Allowance for mechanical ducts should be provided.
The dead load and live load for a typical upper floor in an office building with movable partition walls. The ceiling is a steel channel system and the floors have a linoleum finish. the floors are 3-inch reinforced concrete. Allowance should be provided for mechanical ducts.
An upper floor in a school with steel stud walls (1/2-inch gypsum on each side), a steel channel ceiling system, and a 3-inch reinforced concrete floor with asphalt tile covering. Allowance should be made for mechanical ducts.
Please help problem 1 ( no 1 - 6 ) Problem 1 Use

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!