Question: please help solve this problem you were given that the indirect cost are 200 $ per month, what is the least cost of reducing the

please help solve this problem

please help solve this problem you were given

you were given that the indirect cost are 200 $ per month, what is the least cost of reducing the project completion date by 3 given the following table: Activity Predecessors Normal time Crash time Normal cost Crash cost (months) (months) (USD) (USD) A 6 4 2000 2400 B 7 5 3000 3500 C 7 6 1000 1300 D B 6 4 2000 2600 E D 9 8 8800 9000 m

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!