Question: Please help step by step using excel solver Q3. (10 points) A HOME MNDSCAPTING OPTION IN CAPE BRET ON. NOVA SCOTIA When buyers purchase new
Please help step by step using excel solver

Q3. (10 points) A HOME MNDSCAPTING OPTION IN CAPE BRET ON. NOVA SCOTIA When buyers purchase new homes. they usually choose to do their own landscaping on their new ' property. The PERTICPM network shown in the gure below represents a landscaping project for a new home in Cape Breton. Nova Sootia. The time is measured in days. a. What are the expected completion time and the critical path for the landscaping project in Cape Breton, N.S.? b. What are the earliest and latest start and nish times for activity 0? c. How long can activity A be delayed without delaying the minimum completion time of the project