Topic M 9. Topic ... M Fwd: Appt 2 Nant MT Eignment Sebed 22.33/30 Total points and Problem 18-28 (Algo) The following are historical demand data: YEAR 2011 SEASON Spring Summer Fall Winter Spring Summer Fall Winter ACTUAL DEMAND 285 142 371 580 470 281 692 958 2012 Use regression analysis on deseasonalized demand to forecast demand in summer 2013. (Do not round'intermediate calculations Round your answer to the nearest whole number) Forecast for summer 2013 963