Question: please help with question 2.1 , 2.2 and 2.3 You are the project manager assigned to a project. Use the information given and complete the

please help with question 2.1 , 2.2 and 2.3
You are the project manager assigned to a project. Use the information given and complete the CPM calculations. 2.1 Develop a network diagram. 2.2 Use the table provided to formulate your answer. (5) (15) 2.3 List the critical path. (2) Activity Duration in days A B D E F 2 3 1 5 3 3 Preceding activity Start A A B C, D E Table to use for Question 2.2 ES EF LS LF Float Duration 2 3 Activity A B D E F 1 5 3 3