Question: Please help with the following: Create a Gantt chart Start date is February 7th, 2022. Enter the tasks listed in the work breakdown structure. Assign
Please help with the following:
Create a Gantt chart

Start date is February 7th, 2022.
Enter the tasks listed in the work breakdown structure.
Assign tasks to the available resources so that they can work in parallel as much as possible, and that they can complete the project in as few weeks as possible. Make sure that you assign people only to tasks for which they are qualified. You can assign only one person to a given task.
List the tasks on the critical path.
3 4 Work Breakdown Structure for Software Development Project Task No. Task Name Duration (wks) Predecessors 1 Collect requirements 2 2 Analyze business processes 1 Analyze data 1 4 Design system processes 1,2 5 Design classes and database 2 1,3 6 Design screens 3 4,5 7 Design reports 4 4,5,6 8 Design tests 3 9 Present prototype 1 6,7 10 Re-evaluate requirements 2 9 11 Program all features 5 10 12 Test 6 11 13 Analyze and design documentation 9, 10 14 Write documentation 13 15 Debug and refactor 2 11, 12 16 Test 2 15 17 Deploy 1 14, 16 For this project, you have four human resources: Dimitri: an analyst, programmer and designer, who can also test and write documentation. Sergei: a programmer, who can also collect and evaluate requirements, design classes, databases, screens and reports. Annie: a programmer/analyst, who can also deploy software at the customer's site. Grard: a programmer and tester ! 3 3
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts