Question: please help with the last part, the efficiency % (92.33 is wrong) The following table details the tasks required for Indiana-based Frank Pianki Industries to
please help with the last part, the efficiency % (92.33 is wrong)
The following table details the tasks required for Indiana-based Frank Pianki Industries to manufacture a fully portable industrial vacuum cleaner. The times in the table are in minutes. Demand forecasts indicate a need to operate with a cycle time of 10 minutes. a-b) One of the possible assignment of tasks to workstations is shown correctly in The efficiency of the assembly line with 3 workstations = \% (enter your response rounded to two decimal places)
Step by Step Solution
There are 3 Steps involved in it