Question: Please help with this question! The subject is IT Project Management, See below: Using this excerpt from a COMBINED burn-up/burndown chart (I purposely cut it
Please help with this question! The subject is IT Project Management, See below:

Using this excerpt from a COMBINED burn-up/burndown chart (I purposely cut it off at 14 weeks to save space and allow you to project what the future may bring!) and the cost sheet shown above, answer the following questions. Each question can be answered in one or two sentences.
- Pay attention to the change in the blue scope line. what is the most likely unit(s) of measure along the horizontal line? i.e. sprint, release, project or something else. Why do you think this?
Chart Title Eleven Twelve Thirteen Fourteen Project Scope Cumulative SP's - Remaining SP's --Ideal Progress Timeblock Labor costs $15,000 $15,000 $15,000 $15,000 $15,000 $18,000 $18,000 $18,000 $15,000 $15,000 $15,000 8 9 10
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts