Question: Please help woth red areas Dec. 3 1 Made adjusting entries for the factory that included accrued property taxes of $ 1 4 , 1

Please help woth red areas
Dec. 31 Made adjusting entries for the factory that included accrued property taxes of $14,160, prepaid insurance of $10,384, and accumulated depreciation of $18,880.
(a)
Your answer is correct.
Set up the job cost sheets for Job No. J57 and Job No. K52. Determine the total cost for each manufacturing special order for these jobs. (Round unit costs to 2 decimal places, e.g.12.25.)
Job No. J57
Job No. K52
Total Cost
Unit Cost $
eTextbook and Media
Solution
List of AccountsAccounts Payable
(Purchase of raw materials on account)
Work in Process Inventory
Raw Materials Inventory
(To assign materials to jobs J57 Please help woth red areas
Dec. 31 Made adjusting entries for the factory that included accrued property taxes of $14,160, prepaid insurance of $10,384, and accumulated depreciation of $18,880.
(a)
Your answer is correct.
Set up the job cost sheets for Job No. J57 and Job No. K52. Determine the total cost for each manufacturing special order for these jobs. (Round unit costs to 2 decimal places, e.g.12.25.)
Job No. J57
Job No. K52
Total Cost
Unit Cost $
eTextbook and Media
Solution
List of AccountsAccounts Payable
(Purchase of raw materials on account)
Work in Process Inventory
Raw Materials Inventory
(To assign materials to jobs J57 Please help woth red areas
Dec. 31 Made adjusting entries for the factory that included accrued property taxes of $14,160, prepaid insurance of $10,384, and accumulated depreciation of $18,880.
(a)
Your answer is correct.
Set up the job cost sheets for Job No. J57 and Job No. K52. Determine the total cost for each manufacturing special order for these jobs. (Round unit costs to 2 decimal places, e.g.12.25.)
Job No. J57
Job No. K52
Total Cost
Unit Cost $
eTextbook and Media
Solution
List of AccountsAccounts Payable
(Purchase of raw materials on account)
Work in Process Inventory
Raw Materials Inventory
(To assign materials to jobs J57 Please help woth red areas
Dec. 31 Made adjusting entries for the factory that included accrued property taxes of $14,160, prepaid insurance of $10,384, and accumulated depreciation of $18,880.
(a)
Your answer is correct.
Set up the job cost sheets for Job No. J57 and Job No. K52. Determine the total cost for each manufacturing special order for these jobs. (Round unit costs to 2 decimal places, e.g.12.25.)
Job No. J57
Job No. K52
Total Cost
Unit Cost $
eTextbook and Media
Solution
List of AccountsAccounts Payable
(Purchase of raw materials on account)
Work in Process Inventory
Raw Materials Inventory
(To assign materials to jobs J57
Waterways has two major public-park projects to provide with comprehensive irrigation in one of its service locations this month. Job 157 and Job K52 involve 15 acres of landscaped terrain which will require special-order sprinkler heads to meet the specifications of the project. Using a job cost system to produce these parts, the following events occurred during December.
Raw materials were requisitioned from the company's inventory on December 2 for $5,988; on December 8 for $1,245; and on December 14 for $4,077. In each instance, two-thirds (2/3) of these materials were for J57 and the rest for K52.
Six time tickets were turned in for these two projects for a total amount of 18 hours of work. All the workers were paid $16.50 per hour. The time tickets were dated December 3, December 9, and December 15. On each of those days, 6 labor hours were spent on these jobs, two-thirds (2/3) for J57 and the rest for K52.
The predetermined overhead rate is based on machine hours. The estimated machine hour use for the year is 2,488 hours, and the estimated overhead costs are $1,169,360 for the year. The machines were used by workers on projects K52 and J57 on December 3,9, and 15. Six machine hours were used for project K52(2 each day), and 8.5 machine hours were used for project J57(2.5 the first day and 3 each of the other days). Both of these special orders were completed on December 15, producing 285 sprinkler heads for J57 and 171 sprinkler heads for K52.
Additional job order activities during this period included:
Dec. 1 Purchased raw materials from Durbin Supply Company on account for $62,776.
Dec. 2 Issued $47,200 of direct materials from the company's inventory to
Please help woth red areas Dec. 3 1 Made

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!