Question: Please I need help in this question , Last digit Number is: 8 Last digit Number is: 8 Thank You very much Final exam Q1)

Please I need help in this question ,

Last digit Number is: 8

Last digit Number is: 8

Please I need help in this question , Last digit

Thank You very much

Final exam Q1) The following information has been gathered from a project plan: Activity Duration (Days) Immediate Predecessor A ----- A B A C 5+2* last digit of your student number 4+2*Last digit of your student number 7+2* Last digit of your student number 4+2* Last digit of your student number 3+2*Last digit of your student number 4+2*Last digit of your student number 3+2* Last digit of your student number 4+2*Last digit of your student number 1+2* Last digit of your student number 5+2*Last digit of your student number D E E I F, G J H a) Calculate the duration of each activity using the last digit of your student number. For example, if your student number is EMBA2001124, the last digit is 4 and the duration of activity A is 5+2*4=13. (5 points) b) Construct the project network diagram using AON method. (5 points) c) Calculate ES, EF, LS, LF times for each activity. (10 points) d) Calculate the total slack and free slack of each activity. (5 points) e) Find the critical path(s) and deduce the project duration. (3 points) f) Find one merge activity and two parallel activities. (2 points) BCDEFGH H

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!