Question: Please, I want a solution, I did not understand the question Car factory planned to use $72 of material per unit but actually used $70

Please, I want a solution, I did not understand the question

Car factory planned to use $72 of material per unit but actually used $70 of material per unit, and planned to make 1,200 units but actually made 1,000 units. The flexible-budget variance is
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts