Question: Please include all the work details (20 pts.) For the network diagram below, show, step by step, how you should reduce the project duration. Use

Please include all the work details (20 pts.) For Please include all the work details

(20 pts.) For the network diagram below, show, step by step, how you should reduce the project duration. Use the information in the table below. Activity times are in days. Indirect project cost is $2,000 per day. What is the optimal duration of the project