Question: Please include for S, T, U, V, W, X, Y, and Z. Thanks! The demand for subassembly S is 110 units in week 7. Each

Please include for S, T, U, V, W, X, Y, and Z. Thanks!

Please include for S, T, U, V, W, X, Y, and Z.

The demand for subassembly S is 110 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 1 unit of V, 1 unit of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U. 2 weeks to make V, 3 weeks to make W. 1 week to make X, 2 weeks to make Y, and 1 week to make Z. Click the icon to view the product structure and the time-phased product structure. Click the icon to view the on-hand inventory. Construct a net material requirements plan using on-hand inventory (enter your responses as whole numbers) Week Lead Time (weeks) Item 1 2 3 4 5 6 7 More Info S Gross req On hand 2 Item " On-Hand Inventory 20 20 40 20 On-Hand Inventory 30 25 280 40 Net req Order receipt Order release Item W Y Z T U More Info Print Done The product structure. The time-phased product structure. Level V 0 S W T X 1 (1) U23 Y U zi 2 V) W(1) X(1) Y(2) 2(3) Time in weeks Print Done The demand for subassembly S is 110 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 1 unit of V, 1 unit of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U. 2 weeks to make V, 3 weeks to make W. 1 week to make X, 2 weeks to make Y, and 1 week to make Z. Click the icon to view the product structure and the time-phased product structure. Click the icon to view the on-hand inventory. Construct a net material requirements plan using on-hand inventory (enter your responses as whole numbers) Week Lead Time (weeks) Item 1 2 3 4 5 6 7 More Info S Gross req On hand 2 Item " On-Hand Inventory 20 20 40 20 On-Hand Inventory 30 25 280 40 Net req Order receipt Order release Item W Y Z T U More Info Print Done The product structure. The time-phased product structure. Level V 0 S W T X 1 (1) U23 Y U zi 2 V) W(1) X(1) Y(2) 2(3) Time in weeks Print Done

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!