Question: Please include for S, T, U, V, W, X, Y, and Z. Thanks! The demand for subassembly S is 110 units in week 7. Each
Please include for S, T, U, V, W, X, Y, and Z. Thanks!

The demand for subassembly S is 110 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 1 unit of V, 1 unit of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U. 2 weeks to make V, 3 weeks to make W. 1 week to make X, 2 weeks to make Y, and 1 week to make Z. Click the icon to view the product structure and the time-phased product structure. Click the icon to view the on-hand inventory. Construct a net material requirements plan using on-hand inventory (enter your responses as whole numbers) Week Lead Time (weeks) Item 1 2 3 4 5 6 7 More Info S Gross req On hand 2 Item " On-Hand Inventory 20 20 40 20 On-Hand Inventory 30 25 280 40 Net req Order receipt Order release Item W Y Z T U More Info Print Done The product structure. The time-phased product structure. Level V 0 S W T X 1 (1) U23 Y U zi 2 V) W(1) X(1) Y(2) 2(3) Time in weeks Print Done The demand for subassembly S is 110 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 1 unit of V, 1 unit of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U. 2 weeks to make V, 3 weeks to make W. 1 week to make X, 2 weeks to make Y, and 1 week to make Z. Click the icon to view the product structure and the time-phased product structure. Click the icon to view the on-hand inventory. Construct a net material requirements plan using on-hand inventory (enter your responses as whole numbers) Week Lead Time (weeks) Item 1 2 3 4 5 6 7 More Info S Gross req On hand 2 Item " On-Hand Inventory 20 20 40 20 On-Hand Inventory 30 25 280 40 Net req Order receipt Order release Item W Y Z T U More Info Print Done The product structure. The time-phased product structure. Level V 0 S W T X 1 (1) U23 Y U zi 2 V) W(1) X(1) Y(2) 2(3) Time in weeks Print Done
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts