Question: please include network path The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps.

please include network path
please include network path The Action Toy
The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,800 units per 40-hour workweek: Predecessors Task B C D Performance Time (seconds) 20 30 15 15 10 30 mmo A A A B, C DE This exercise only contains parts b, c, d, e, and I b) Given the demand, the cycle time for the production of the new train set = seconds (round your response to one decimal place)