Question: please include network path The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps.
please include network path
The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,800 units per 40-hour workweek: Predecessors Task B C D Performance Time (seconds) 20 30 15 15 10 30 mmo A A A B, C DE This exercise only contains parts b, c, d, e, and I b) Given the demand, the cycle time for the production of the new train set = seconds (round your response to one decimal place)