Question: please include the following : 1- MPS quantity 2- MPS start 3- Available-to-promise (ATP) inventory An end item's demand forecasts for the next 6 weeks

please include the following :
1- MPS quantity
2- MPS start
3- Available-to-promise (ATP) inventory
An end item's demand forecasts for the next 6 weeks are 35 units, followed by forecasts of 25 units for weeks 7 though 10 . The current on-hand inventory is 70 units. The order policy is to produce in lots of 110. The booked customer orders for the item, starting with week 1 , are 17, 35, 10, 11, 0,0,12,0,0, and 0 units. The lead time is 2 weeks. a. Develop an MPS for this end item. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.)Step by Step Solution