Question: Please include with the submittal a Work Breakdown table, Gantt chart, cumulative cost curve, and a AON Network diagram for both the lift station example

Please include with the submittal a Work Breakdown table, Gantt chart, cumulative cost curve, and a AON Network diagram for both the lift station
example and your individual project. The lift station design timeline is as follows:
Layout Site (Civil)-1 week to complete
Layout Process Piping and Equipment (Mechanical)-2 weeks to complete
Layout Building (Architectural)-4 weeks to complete
Structural Building Design (Structural)-4 weeks to complete
Mechanical Systems Design -2 weeks to complete
Electrical Systems Design -2 weeks to complete
Internal/External Review -1 week to complete
You may pick your own dollar amounts as to the cost of each deliverable listed above in preparing the cumulative cost curve for the lift station as
you will for the individual project.
 Please include with the submittal a Work Breakdown table, Gantt chart,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!