Question: Please indicate which order the following steps in the Material Planning Process happen in: Question 21 options: 123456789 Create revised PIRs (Planned Independent Requirements) for
Please indicate which order the following steps in the Material Planning Process happen in:
Question 21 options:
| 123456789 | Create revised PIRs (Planned Independent Requirements) for each material using SOP PIRs and fulfillment's actual requirements. |
| 123456789 | Create a sales plan at the product group level. |
| 123456789 | The Material Planning Process is complete |
| 123456789 | Calculate net requirements of material using purchase requirements, purchase orders, goods receipt, sales orders, deliveries, goods issues, planned production orders, production orders, material reservations, and goods receipts through MRP. |
| 123456789 |
A need or desire to revise the organization's production plan. |
| 123456789 | Create an operations / production plan at the product group level. |
| 123456789 | Create purchase requisitions, planned orders and dependent requirements. |
| 123456789 | Transfer PIRs (Planned Independent Requirements) for each period into demand management. |
| 123456789 | Disaggregate operations / production plans at the product group into a plan for the materials contained in those groups. |