Question: please let me know the answes for this Question 15 (1 point) A project consists of seven activities. The following table shows the estimated time

please let me know the answes for this
please let me know the answes for this Question
Question 15 (1 point) A project consists of seven activities. The following table shows the estimated time of the activities and the precedence relations. Estimated Immediate Activity durations (days) predecessor 9 10 C 5 . 3 A 6 B, C 3 B, C 4 DE If the duration of activity B increases by 3 days, by how many days will the project duration increase? Your