Question: please look at multiple choice answers and provide a solution. please show step by step working out Trucks arrive randomly at the average rate of
please look at multiple choice answers and provide a solution.
Trucks arrive randomly at the average rate of 5 per hour. A team of two warehouse workers can unload trucks at the rate of 6 per hour. Each warehouse worker receives $20 per hour. Each idle truck will be charged $100 per hour penalty for waiting. What is the expected total costs? (Total costs - Labor cost + Penalty of idle truck) $456.67 perhour $416.67 per hour 5164.17 per hour $13000 per hour
please show step by step working out