Please make a network Diagram using the table (Please write out on paper using the proper act and duration with circle and lines) Also use the gerenal sequence of activites 1st exacation, piles driven, footer (forming, pouring, curing, stripping), abutment (forming, pouring, curing, stripping, rub),girders, Deck (forming, pouring, curing, stripping). Restrictions are that there is only one exacation crew and on;y set of formwrok material for footers and abutment. Duration of project is approx 65 day. Please read the hints and restrictions!