Question: please need it now Suppose you are a project manager in a big manufacturing company. In order to determine the expect time of the project

please need it now

Suppose you are a project manager in a big manufacturing company. In order to determine the expect time of the project you have to know each activity duration and it is precedence to execute the project effectively and efficiently. Given the following data.

Consider the following project:

Activity

Immediate predec.

Optimistic time (hr)

Most likely time (hr)

Pessimistic Time (Hrs)

A

-

3

2

1

B

-

5

2

8

C

A

3

1

4.5

D

B

5

2

3

E

C,D

2

6

2

F

E

1

7

7

G

F,E

1.5

4

8

A) Explain the precedences of each activity the network (5 Marks)

B) Calculate the expected time for each activity (5 Marks)

C) Calculate the variance for each activity (5 Marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!