Question: Please only answer if you know it for a fact (10. Q1 Part B) The allowances for tasks such as this are personal, 6%; fatigue,
Please only answer if you know it for a fact (10. Q1 Part B)
The allowances for tasks such as this are personal, 6%; fatigue, 12%; and delay, 4%. a) The normal time for the complete operation = minutes (round your response to two decimal places). b) The standard time for this process = minutes (round your response to two decimal places)