Question: PLEASE ONLY USE THE EXCEL MPR TABLE FORMAT, please provide the table Eighty units of end item E are needed at the beginning of week

Eighty units of end item E are needed at the beginning of week 6.30 units of F are scheduled to arrive in week 2. There are 60 units of B and 20 units of F now on hand. Lead times are two weeks for E and B, and one week for F. Prepare a material requirements plan for E, B and F. The table used in MRP is as follows: Master Schedule