Question: Please prepare a construction schedule using any software based on the following information: The Contract starts on May 1, 2019 and ends on November 28,

Please prepare a construction schedule using any software based on the following information:

  • The Contract starts on May 1, 2019 and ends on November 28, 2020
  • A typical construction season has 119 working days
  • A typical construction season in Ontario starts on the first Monday of May and ends on the last Saturday of November
  • Michael Road Underpass = 120 working days; No bird preventative measures required; cannot be closed; only staged construction allowed.
  • Eileen Road Underpass = 35 working days; Must be closed for construction; Must be completed by June 15, 2020; Cannot be staged construction while Michael Road Underpass is staged; Cannot be closed in 2019 construction season; No bird preventative measures required.
  • Larry Road 110 = 40 working days and Larry Road 115 = 50 working days; Bird preventative measures required i.e. either the bird kiosks must be installed before the start of the work; Construction cannot happen at the same time on both structures
  • Ravi Road Underpass = 45 working days; must be completed by June 30, 2020; Must be closed for construction
  • Sherry Bridge Underpass = 40 working days; Must be closed for construction; Bird preventive measures required
  • Construction can start after Sep 1 to avoid bird preventive measures

  1. Please prepare a Gantt Chart Schedule using any software showing the possibilities of the construction 2 Marks

  1. Please prepare one construction sequence as a Gantt Chart using any software

which you will follow if you are a contractor 2 Marks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!