Question: Please provide complete solution, thank you Equipment Scheduling You are to undertake a condominium project with two high - rise buildings. Given the constraints that

Please provide complete solution, thank you Equipment Scheduling
You are to undertake a condominium project with two high-rise buildings. Given the constraints that the site only has one excavator and one tower crane, analyze the activities below to give the shortest possible duration of the project.
\table[[Construction Phase(s),Tower A,Tower B],[\table[[Earthworks],[(Requires Excavator)]],5 months,6 months],[Foundation Works,4 months,4 months],[Building Superstructure,8 months,10 months],[\table[[Pre-cast Panel Installation],[(Requires Tower Crane)]],9 months,5 months],[Architectural Finishes,5 months,8 months]]
Earned Value
As the Project Manager of a low-cost housing project by NHA, your objective is to build four (4) houses per month at a cost of PhP 900,000 each, completing the project in 12 months. You are now in the beginning of your 8 th month and was able to build 30-houses. Moreover, upon evaluating the project's current Cost Performance Index (CPI) is at 0.8750.
a. What is the actual project cost to date?
b. What is the estimated cost at completion using the CPI and SPI of the Project?
c. Project Progress is currently at what percentage?
Please provide complete solution, thank you

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!