Question: Please provide graphs and excel 8. (12 points): Given the following data, fill the blanks in the table. Note that a,m, and b are in


Please provide graphs and excel
8. (12 points): Given the following data, fill the blanks in the table. Note that a,m, and b are in days. Answer all the questions below. Show your formulas and/or details where appropriate. Draw the CPM diagram here: Draw the CPM diagram here: Critical Path: Expected Project Completion Time: Standard Deviation of Project Completion Time: Probability of completing the project in 38 days: Find the time where the probability of project being delayed is 0.01 or less
Step by Step Solution
There are 3 Steps involved in it