Exercise 1: Assembly line balancing Given the following precedence graph (and task operation times in minutes): Assume that 18 items of this product have to be produced within 3 hours. a) Calculate the cycle time. b) Calculate a lower bound for the number of stations. c) Calculate an upper bound for the number of stations. d) Assign task to stations using the position value. e) Calculate the system's efficiency. Exercise 1: Assembly line balancing Given the following precedence graph (and task operation times in minutes): Assume that 18 items of this product have to be produced within 3 hours. a) Calculate the cycle time. b) Calculate a lower bound for the number of stations. c) Calculate an upper bound for the number of stations. d) Assign task to stations using the position value. e) Calculate the system's efficiency

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!