Question: Please provide the following for a 3-week deck construction project plan consisting of the following activities in order: 1) design/permits, 17 days 2) Site grading,

Please provide the following for a 3-week deck construction project plan consisting of the following activities in order:

1) design/permits, 17 days

2) Site grading, 4 days

3) Foundation, 3 days

4) Wood framing, 4 days

5) decorate finishes, 4 days

6) electrical, 5 days

7) final clean. 1 days

The cost for the entire project is $5K down & $5K at completion for a total of $10K to be completed in a 3 week time frame.

Please provide the predecessor and successor, develop a network diagram, find the critical path and estimate early start, early finish, and slack time for all activities in days.

Thanks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!