Question: Please quickly I have limited time on final test pl In the Harrelson Company, indirect labor is budgeted for $36,000 and factory supervision is budgeted
Please quickly I have limited time on final test
pl
In the Harrelson Company, indirect labor is budgeted for $36,000 and factory supervision is budgeted for $12,000 at normal capacity of 80,000 direct labor hours. If 90,000 direct labor hours are worked, flexible budget total for these costs is a) $49,500. b) $48,000 c) $52,500. d) $54,000