Question: please quickly Question #3 ( 15 points) The table below shows a project activity and three-point estimates. (Show a sample of your calculations) PAGE 1

please quickly
Question #3 ( 15 points) The table below shows a project activity and three-point estimates. (Show a sample of your calculations) PAGE 1 Precedes Activity A Pessimistic Duration in days Most Likely 6 Optimistic 5 7 B 8 11 6 8 11 F 12 15 END 6 9 Uow I 00 Onn F G 6 7 G END 3 7 1 4 5 1 END 7 8 a) Construct the project network (activity-on-node diagram). List all the paths of the project network b) what is the completion time for this projectStep by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
