Question: PLEASE READ BACKBGROUND AND EXISTING FACILITIES THEN ANSWER THE QUESTIONS IN DETAIL. Project background: Leeds Water Limited ( LWL ) operates a wastewater treatment plant

PLEASE READ BACKBGROUND AND EXISTING FACILITIES THEN ANSWER THE QUESTIONS IN DETAIL.
Project background:
Leeds Water Limited (LWL) operates a wastewater treatment plant that was built in the 1960s for the town of Jeddah Ali, population equivalent of 12,500. Jeddah Ali Sewage Treatment Works (STW) is an activated sludge treatment plant that treats an average flow of 3.3 million litres per day (Ml/d). The plant was commissioned in 2002 after a conversion from trickling filter to an activated sludge and the current consent that the plant must meet is 25/45/5(BOD/SS/NH4) on a 95-percentile basis. In November 2017; the treatment plant was required to meet an annual average phosphorus limit of 1 mg/l in addition to the current limits for BOD, SS and ammonia. The Jeddah Emirate Council approved the building of a petrochemical plant in the industrial estate close to Jeddah Ali STW. An agreement has been reached with GWL to treat the wastewater from the petrochemical plant at GWL STW. Production is expected to start in September 2016 with an estimated oily wastewater of 2 Ml/d and a COD of 560 mg/l.
Existing Facilities:
Figure 1 show the top view and figure 2 the plan view of the existing activated sludge basins at the Jeddah Ali STW. It is a pocket ASP design, fully nitrifying plant with anoxic and aerobic basins. There is one (1) anoxic basin, divided into two sections by a baffle wall, followed by four (4) aerobic basins. The basins are run at a maximum design mixed liquor suspended solids (MLSS) of 3000 mg/l. The plant also has two (2)12 m diameter, circular final settling tanks with a net surface area of 225 m2. The activated sludge process is preceded by fine screens, grit removal and circular primary settling tanks. Table 1 summarizes the existing secondary facilities.
TASKS:
1. Check the adequacy of the existing plant to cope with the additional loads by investigating the various operational parameters. If not, what could be done to continue to meet consents.
2. Design a new sludge treatment plant to deal with the total sludge and estimate the potential electricity generation from the plant (make any necessary assumptions and provide justifications).
3. Review retrofit options for removing SARS-CoV-2(the virus that causes COVID-19). Prior to the outbreak, most wastewater treatment works were not intentionally designed for SARSCoV-2 removal. In addressing this, the following points should be considered:
- In what form does the virus exist in wastewater?
- How is the virus detected?
- How is the virus removed from wastewater; and at what point/stage in the treatment stage/process?
PLEASE READ BACKBGROUND AND EXISTING FACILITIES

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!