Question: Please read Lecture 5 slides 4 7 - 6 7 . The problem below is similar to the example for a construction project in slides

Please read Lecture 5 slides 47-67. The problem below is similar to the example for a construction
project in slides 63-67.
A project consists of 10 work packages (activities A J). Your instructor has developed a network
diagram and used CPM to find the critical path. The activities along the critical path are A-C-D-G-I-J.
Activity
Time Estimates (Duration)
in days
Low Mode High
A 91622
B 81420
C 568
D 161823
E 223033
F 71012
G 212429
H 5810
I 121821
J 246
a) Find the expected duration of the project, its variance and standard deviation
b) Whats the probability (expressed in %) of completing the project in more than 13 weeks?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!