Question: Please refer Figure and Table for design bridge construction CPM network schedule. 3 - 1 Please develop a precedence diagram for this bridge construction project
Please refer Figure and Table for design bridge construction CPM network schedule. Please develop a precedence diagram for this bridge construction project
calonlate eardy start, late start eardy inish late finish and total foat
What is the total completion duration?
What is the critical path?
Based on your identified critical path, please discuss how you cam handile
your scheduleif the task of "Pouring Foot at the Abutment has been delayyed days. Is there any effect on your total project completion date?