Question: Please refer to the table given below. Considering that the project has a negative float of three months, which of the following task(s) should be

Please refer to the table given below.

Please refer to the table given below. Considering that the project has a negative float of three months, which of the following task(s) should be crashed to bring the project on schedule? Task Q Task N and Task 0 Task Original Duration (months) 5 6 M N Either Task Q or Task N and Task 0 Crash Duration Original (months) Cost 1 $1,600 2 $1,800 1 $2,000 1 $3,000 3 $2,500 Crash Cost $1,700 $1,900 $2,050 $3,200 $2,650 0 7 8 Task N and Task P Q 13